Waterval Smelter – Stack Replacement

Date: 19 August 2019

City: Rustenburg

Scope of work: Stack Replacement Anglo Platinum Waterval Smelters ACP

Lift Specification: 39 Meters, Height 88m 6 Ton

Challenges: Height; August – Windy month, crane work was stopped 1 time

Solutions Provided (Equipment): Push main boom up with luffing,Make use of the 750 Ton Crane, Luffing 56 meters

Methods of Execution: Crane at Waterval ACP – Was build by a 75 ton (LH114) crane; Stack has Phase A and a Phase B both was cut and removed in 6m pieces (8 pieces)

Benefits to Customer: Work done safe; No hold ups from JCH side